In early 2025, a leading US cloud provider faced surging AI/HPC workloads requiring rapid capacity expansion, but traditional 18–24 month data center builds were unacceptable. The North American containerized data center market, valued at $6.88B in 2025 and projected at $23.96B by 2031 (CAGR 23.10%), offered faster, efficient, scalable solutions.
Solution: INFINITY SERIES – fully integrated, factory-preassembled modular system, pre-tested and pre-commissioned, reducing on-site construction time by 50–70%. Modular architecture scales from 5 MW to 50 MW per block, supporting mixed IT loads and extreme rack densities for AI/HPC, enabling incremental expansion and lower upfront capex.
Deployment: 5 × 40‑ft ISO containers, each factory‑integrated with racks, power, cooling, monitoring, and physical security. The 40‑ft form factor balances transportability and capacity.
Power Density: 100 kW/rack – engineered for modern AI/HPC (typical 30–80 kW, leading deployments >100 kW), far beyond traditional 2–5 kW/rack.
IT Capacity: 5.0 MW total (five containers × 100 kW/rack).
UPS Redundancy: 2N architecture – two independent power paths ensure zero downtime on single component failure.
Battery Backup: 10‑minute Li‑ion runtime at full load, bridging utility-to-generator transition; superior energy density, faster recharge, longer cycle life than VRLA.
Cooling: Air‑cooled magnetic bearing chiller with free cooling, plus hybrid air/liquid‑cooling. Magnetic bearing chillers eliminate oil lubrication, improve efficiency. Free cooling reduces mechanical energy in favorable ambient conditions. Hybrid architecture supports both legacy air‑cooled servers and liquid‑cooled GPU clusters, enabling densities from 50 kW to >100 kW per rack.
Fire Safety: Novec 1230 clean agent suppression + VESDA aspirating smoke detection. Novec 1230 avoids water damage to IT equipment; dual‑circuit initiation (VESDA fourth‑stage alarm + point‑type detection) ensures earliest response.
Monitoring: Integrated DCIM provides real‑time visibility into power, thermal performance, and equipment health across all containers, enabling predictive maintenance, capacity planning, and automated optimization.
This INFINITY SERIES deployment delivered 5 MW capacity within six months, meeting aggressive timelines while ensuring reliability, scalability, and energy efficiency – a turnkey answer to the US provider’s critical capacity crunch.